Bond Project Information
Original Project Budget: $6,200,000
Revised Project Budget: $6,703,500
Construction GMP: $5,603,500
Bond Issuance Date: April 2021
Construction Start Date: October 2021
Estimated Completion Date: December 2022
Architect: FWA Group
Construction Manager-At-Risk: NA
Building Square Footage: 27,400
Operating Impact: $114,324
Student Services Center (27,400 SF):
• Academic Advising
• Admissions/Registration
• Veteran Services
• Disability Services
• Counseling Services
• Career Services
• Financial Aid
• Student Payment Services

Student Services Learning
Bond Project Updates
Click on the description to see information regarding bond project progress.
The project continues to remain on budget and is approximately 97% complete as of 12/22/2022. The contracted completion date of 12/16/22 was not met by the contractor. The building is close to completion, the final painting is underway, carpet installation is almost complete, and the final data line installation is ongoing. Exterior work has been delayed due to the rainy conditions slowing down the completion of sidewalks and curbs. The College is working to complete the final fiber connections to the building and install switches in the IT closet. The contractor understands if they cannot have a final certificate of occupancy by 1/9/23, they will have to take responsibility for new furniture storage costs and may also be subject to $300 per day in liquidated damages back to 12/17/22. The College is still planning to move staff into the building starting 1/30/23.