Public Safety Training Center

Proposed Bond Project Information

Project Budget: $10,400,000

Bond Issuance Date: September 2022
Project Start Date: May 2022
Construction Start Date: November 2022
Estimated Completion Date: December 2023
Architect: Moseley Architects
Construction Manager-At-Risk: Samet Corportation
Operating Impact: $136,965

Public Safety Training Center

Public Safety Center:
• 15,000 SF with 24 lanes
• Six Classrooms adjoining Indoor Firing Range and Fire Tower
• Dedicated Shooting Simulator Space
• Basic Law Enforcement Training
• Driving Pad
• Emergency Medical Services (Future)

Public Safety Training Center
Bond Project Updates

Click on the description to see information regarding bond project progress.

The College received the latest construction cost estimate from Samet and the third-party estimator on December 6th. The new December estimate increased by $507,183 over the July 2022 estimate. The major contributing factor is additional escalation due to the later July 2023 bid date. Overall the project budget shortfall based on the new estimate is $5,691,515. If the Indoor Firing Range is removed from the project, the overall project budget shortfall would be $127,221 which could most likely be resolved through additional value engineering within the remaining scope of the project. The College continues to explore opportunities for additional funding for the building of the Indoor Firing Range.

The design team has submitted the schematic design package to State Construction for review and approval and is currently working on the design development documents.