Student Services Learning & Development Center

Bond Project Information

Original Project Budget: $6,200,000

Revised Project Budget: $6,703,500

Construction GMP: $5,603,500

Bond Issuance Date: April 2021
Construction Start Date: October 2021
Estimated Completion Date: February 2023
Architect: FWA Group
Construction Manager-At-Risk:
NA
Building Square Footage:
27,400
Operating Impact:
 $114,324

Student Services Center (12,203 SF):
• Academic Advising
• Admissions/Registration
• Veteran Services
• Counseling Services
• Financial Aid
• Student Payment Services

ACC Student Services Building

Student Services Learning
Bond Project Updates

Click on the description to see information regarding bond project progress.