General Information
Year Built: 1950
Building Area: 256,767 SF
Acres: 23.57
Classroom Capacity: 1,180
Number of Students: 1,170
Current Capacity: 99.15%
Project Start Date: January 2020
Bond Issuance Date: April 2021
Construction Start Date: July 2021
Completion Date: December 2022
Bond Project Information
Project Budget: $4,646,400
Construction GMP: $3,781,092
Renovate/Upgrade Existing Buildings to include:
• School safety improvements (cameras, blinds, carded entry locks)
• Exterior window replacement & caulk where needed
• Renovate multi-restroom facilities with new plumbing fixtures, tile, partitions and paint
• Remove media center carpet; replace with tile
• Replace non-ADA compliant cabinets, sinks, door hardware
• Replace auditorium seating and
carpet/remediate/remove remaining asbestos
• Add restrooms for auditorium area
• Repair structural issues at exterior auditorium stairs
• Re-key building
• Roof replacement/repairs where needed
Williams High School Bond Project Updates
Click on the description to see information regarding bond project progress.
ABSS is currently working on a punch list.
Williams High School Capital Projects
Capital Projects in Progress
- 2020: Track Repairs and Resurfacing
- 2019: Williams High Transformer Relocation $200,000
Capital Projects Completed
- 2020: Plaster Repair
- 2020: Installation of ADA Concrete
- 2020: Installation of Wheel Chair Lifts
- 2020: Installation of ADA Home Economics Stations
- 2020: Painting
- 2016: Door Replacement $23,767.44
- 2016: Parking Lot Striping $1,375.00
- 2016: Bathroom Partition Replacement $5,600.00