General Information
Year Built: 1962
Building Area: 151,000 SF
Mobile Unit Square Footage: 1,500 SF
Acres: 42.2 (incl. N. Graham)
Classroom Capacity: 915 Students
Number of Students: 715
Current Capacity: 78.14%
Project Start Date: January 2020
Bond Issuance Date: April 2021
Construction Start Date: July 2021
Completion Date: January 2023
Bond Project Information
Project Budget: $7,619,063
Construction GMP: $6,019,889
1. Renovations/upgrades to existing buildings
2. Purchase equipment for specialized trades programs
Renovate/Upgrade Existing Buildings to include:
• School safety improvements (cameras, blinds, carded entry locks)
• Flooring replacement including removal/abatement of remaining
asbestos tiles
• Exterior window replacement & caulk where needed
• Renovate multi-restroom facilities with new plumbing fixtures, tile, partitions and paint
• Remediate cracking in concrete masonry block walls
• Provide tempered water at eye wash stations in shop areas
• Replace non-ADA compliant cabinets, sinks, door hardware
• Roof replacement or repairs where needed
• Add humidity controls to HVAC where needed
• Replace campus walkway canopy system
• Replace chorus room platform
• Repair damaged sidewalks and curbs
Graham High School Bond Project Updates
Click on the description to see information regarding bond project progress.
ABSS is working on an extended punch list. Graham High has a complete certificate of occupancy.
Graham High School Capital Projects
Capital Projects in Progress
- 2020: Track Repairs and Resurfacing
Capital Projects Completed
- 2020: Installation of ADA Concrete
- 2020: Installation of Front Office ADA Furniture
- 2020: Installation of Flooring
- 2020: Installation of ADA Home Economic Stations
- 2016: Parking Lot Striping $1,150.00
- 2016: Bathroom Partition Replacement $7,400.00
- 2016: Painting $179,750.00