General Information
Year Built: 2007
Last Renovation: NA
Gross Area (SF): 9,638
Rating: A
Departments: Emergency Medical Services (EMS)
EMS Substation Mebane Expansion
COST ESTIMATE: $3,540,000
Expected Borrowing Date: October 2022
Construction Start Date: TBD
Estimated Completion Date: TBD
Operating Costs: TBD
EMS Substation: 425 Rudd Street, BurlingtonĀ
Year Built: 2001
Last Renovation: NA
Gross Area (SF): 2,584
Rating: B
EMS Substation: 511 Boone Station Drive, Burlington
Year Built: 2001
Last Renovation: NA
Gross Area (SF): 3,756
Rating: B
Ambulance Garage: 118 W. McAden Street, Graham
Year Built: 1959
Last Renovation: NA
Gross Area (SF): 5,490
Rating:

Capital Projects In Progress
Upcoming Capital Projects
- 2022-2023: EMS Substation Mebane Expansion $3,540,000
- 2021-2022: Rudd Street EMS Station Concrete Pad Upgrades (Extended to parking areas) $16,900
- Unassigned: Rudd Street EMS Station Roof Replacement $20,000
Completed Capital Projects
- 2020-2021: EMS Headquarters Office Renovation $16,500
- 2019-2020: Roof Repair and Maintenance at EMS Garage
- 2018-2019: EMS - Boone Station Concrete Project
- 2018-2019: EMS - Boone Station and Rudd Street Station Generators