Cummings High School

2200 N Mebane St, Burlington, NC 27217

General Information

Year Built: 1970
Building Area:
194,300 SF
Acres:
73.5 (incl. Broadview)
Capacity: 880 Students
Number of Students: 1,007
Current Capacity: 114.43%
Project Start Date: January 2020
Bond Issuance Date: April 2021
Construction Start Date: July 2021
Completion Date: January 2023

cummings

Bond Project Information

Project Budget: $10,867,063

Construction GMP: $9,965,563

Completed project will include:
• Auditorium lobby addition
• Renovations/upgrades to existing buildings
• Purchase specialty equipment for Fine Arts
programs

Renovate/Upgrade Existing Buildings to include:
• School safety improvements (cameras, blinds, cardedentry locks)
• Exterior window replacement & caulk
• Renovate multi-restroom facilities withnew plumbing fixtures, tile, partitions and paint
• Replace non-ADA compliant cabinets, sinks, door hardware
• Update acoustics, rigging, lighting and A/V systems in auditorium
• Replace carpeting and seating in auditorium
• Replace sheet carpeting and vinyl/composite tile
• Remediate poor drainage at parking lots and around buildings
• Re-key building

Cummings High School Bond Project Updates

Click on the description to see information regarding bond project progress.

The completion date for Cummings High School has changed from March 1 to April 28. The auditorium and fine arts remodel are in process. The remodel of the ceramic art class cannot start until the auditorium and fine arts remodel is complete. The dance classroom is near complete once the dance rail is installed and the inspection has been completed. The school is awaiting grade work at the front entrance.

Cummings High School Capital Projects

Capital Projects in Progress

Capital Projects Completed

  1. 2020: Installation of ADA Concrete
  2. 2020: Installation of Parking Lot Striping
  3. 2020: Installation of Fire Doors
  4. 2020: Installation of ADA Parking
  5. 2020: Installation of Front Office ADA Furniture
  6. 2020: Installation of Flooring
  7. 2020: Installation of Home Economic Stations
  8. 2019 - Plaster fixed at CHS/ceilings, repair paint
  9. 2019 - Remodel Chorus and Band Room $100,000
  10. 2019 - Roofing project completed $1,199,032
  11. 2016 - Media Carpet Removal $22,000
  12. 2016 - Door Replacement $12,175
  13. 2016 - Parking Lot Striping $2,675
  14. 2016 - Roof Evaluation $7,750
  15. 2016 - Bathroom Partition Replacement $12,500
  16. 2016 - Gym Floor Replacement $140,987